Project Overview

Project Name: Baltica 2 Offshore Substation Project

Project Description: PowerMore provides specialized technical services supporting the installation, testing and commissioning of major electrical equipment at the offshore substations of the Baltica 2 project. The scope of work includes electrical testing, vacuum treatment, insulating oil filtration and equipment acceptance prior to energization and operation.

Category Details
Industry / Sector Offshore Wind Power
Project Type Offshore Substation (OSS)
Voltage Level 275 kV (Baltica 2 transmission voltage)
Main Equipment 225 MVA power transformers and 140 MVAr shunt reactors
Project Scale 4 offshore substations, each rated at 375 MW
Location Baltic Sea, Poland
Implementation Period 2026

PowerMore’s Scope of Work

PowerMore carries out specialized technical services to support the installation, testing and commissioning of major electrical equipment across the Baltica 2 offshore substations.

✓ Pre-installation testing of primary electrical systems for power transformers and shunt reactors.

✓ Site acceptance testing of primary electrical systems for power transformers and shunt reactors.

✓ Vacuum treatment and insulating oil filtration for power transformers.

✓ Vacuum treatment and insulating oil filtration for shunt reactors.

Equipment Covered

  • 8 × 225 MVA power transformers (2 transformers per OSS)
  • 4 × 140 MVAr shunt reactors
  • Equipment supplied by HD Hyundai Electric

Project Highlights & Value

Technical Services for a Large-Scale Offshore Substation System

PowerMore provides technical services for 4 offshore substations, each with a capacity of 375 MW, as part of one of Poland’s major offshore wind power developments.

The project requires technical execution in a demanding offshore power infrastructure environment, with a strong focus on equipment quality, testing accuracy and readiness for commissioning.

Comprehensive Testing and Commissioning Support for Major Electrical Equipment

PowerMore’s scope covers critical stages from pre-installation testing through on-site acceptance testing, vacuum treatment and insulating oil processing.

These activities are carried out to help ensure that transformers and shunt reactors meet the required technical conditions before energization, commissioning and commercial operation.

Supporting High-Capacity Power Equipment

The technical scope covers major high-capacity electrical equipment, including:

  • 8 × 225 MVA power transformers
  • 4 × 140 MVAr shunt reactors

The scale and capacity of the equipment require controlled testing procedures, specialized technical expertise and strict compliance with project acceptance requirements.

Contributing to Installation Quality and Equipment Readiness

PowerMore’s technical services support the verification of equipment condition and installation quality before the main electrical equipment is placed into service.

Through electrical testing, vacuum treatment and insulating oil filtration, PowerMore contributes to ensuring that the transformers and shunt reactors are properly prepared for energization and reliable operation within the Baltica 2 offshore substation system.

Newsletter Updates

Enter your email address below and subscribe to our newsletter

Leave a Reply

Your email address will not be published. Required fields are marked *

Zalo Zalo Linkedin Linkedin

Send Your Message

Contact Form